03/14/2019 IL Route 31 Construction Update

Pavement Patching at the intersection of Lincoln and Main
Compaction of a Sanitary Sewer Trench

Utility relocation work will be completed in the next few weeks.  Over the next two weeks you will see an increased construction presence.   The entire construction zone will be restriped.  Sanitary sewer installation is expected to be completed next week. Pavement breaking may begin in the areas behind the concrete barriers as early as tomorrow.  After completion of the pavement breaking, pavement removal and water main installation will occur in the same locations.