07/17/2020 IL Route 31 at Huntley Road Construction Update

Rebar Installation for Caissons on Main Street
Pavement Breaking on IL Route 31

This week, installation of the 1st stage of caissons was completed on Main Street, East of IL Route 31, all pavement removal was completed on both the North and South sections of IL Route 31 and storm sewer was being installed on both the North and South sections of IL Route 31.  Next week, excavation will begin for the new pavement on IL Route 31 and caisson installation will continue.