07/22/2019 IL Route 31 Construction Update

Driveway Pavement Removal at Parkway Bank
Roadway Removal on Lincoln
Driveway Pavement Removal on South Lincoln

Water main service and sanitary service installation continues. Filling of the abandoned 16" water main is anticipated to be completed by the end of the week. Comcast and AT&T relocation work is continuing. Excavation for the retaining wall at the Northeast corner of IL Route 31 and Main Street will begin within the next week or two after utility relocation.