This week, the traffic switch was implementation on Monday, traffic signal mast arms and poles were installed at Spruce, concrete pavement was placed on the North end of IL Route 31 and the retaining walls were stained.
Next week, concrete pavement will be placed on the Main Street hill and the North end of IL Route 31, storm sewer will be installed on Huntley Road West of IL 31, and landscaping will begin throughout the project.