09/26/2020 IL Route 31 at Huntley Road Construction Update

Concrete Paving up the Main Street Hill

Completed Pavement on the Main Street Hill

This week, storm sewer installation, excavation and stone placement was completed on Huntley/Main, West of IL Route 31, concrete pavement was placed on North and South sections of IL Route 31 and the Main Street hill, traffic signals were installed at Spruce and Huntley/Main and street/pedestrian lighting was installed at the Lincoln/Main Street intersection.

Next week, curb and gutter will be placed on Huntley Road, West of IL Route31  and on the northern section of IL Route31,  and the median on IL Route 31 South of Huntley will be poured.

On Wednesday, traffic will be shifted to the inside lanes on IL Route 31.  This will allow left turns into Aldi and Spruce.   No left turns (N and E) at 31/Huntley will continue.