10/18/2019 IL Route 31 Construction Update

Preparation of the NW Corner of IL Route 31 and Huntley for Concrete Pavement
Placement of Concrete Pavement at the Corner of IL Route 31 and Huntley Road

Placement of the asphalt base and binder was completed on Huntley Road, East of IL Route 31. All driveway aprons on the North side of Huntley Road will be completed by the end of the day.  Next week, work is anticipated to begin on the shared use path on the North side of Huntley Road.  Main Street entrances at  Otto Engineering are anticipated to be completed next week.  The final lift of asphalt for North and South Lincoln and the section of Main from Lincoln East to the bridge will be placed after completion of the Otto driveway entrances.  The retaining wall located at the NE corner of IL Route 31 and Main Street will be completed by the end of the day.