10/25/2019 IL Route 31 Construction Update

Completed Concrete Retaining Wall at the NE Corner of IL Route 31 and Huntley Road
Concrete Pavement Pour at the NW Corner of IL Route 31 and Huntley Road

The retaining wall located at the NE corner of IL Route 31 and Main Street  and the shared use path on the North side of Huntley Road has been completed this week. Work on the Main Street entrances at Otto Engineering have begun and are anticipated to be completed next week. The final lift of asphalt for North and South Lincoln and the section of Main from Lincoln East to the bridge will be placed after completion of the Otto driveway entrances.