11/01/2019 IL Route 31 Construction Update

Excavation for Sidewalk on the South Side of Main Street
NE Corner of IL Route 31/Huntley Road Retaining Wall Backfilled

The retaining wall located at the NE corner of IL Route 31 has been completed and backfilled.  Work on the Main Street entrances at Otto Engineering has begun and are anticipated to be completed next week, weather permitting.  The final lift of asphalt for North and South Lincoln and the section of Main from Lincoln East to the bridge will be placed after completion of the Otto driveway entrances, weather permitting.