11/08/2018 IL 31 Weekly Construction Update

New water service installation to residents and businesses on Main/Huntley between Elm and IL Route 31 will as early as tomorrow. Demolition of 15 N. IL Route 31, located at the Northwest corner of IL Route 31 and Main Street, has been completed. Nicor utility work will continue North of Main Street on IL Route 31, on the west side of the road.  Currently,the contractor is waiting for their work plan to be approved by Nicor due to the construction work occurring over and around Nicor’s high pressure gas main.