11/16/2018 IL Route 31 Weekly Update

Directional Drilling Water Services

New water service installation to residents and businesses on Main/Huntley between Elm and IL Route 31 will continue until complete.   Next week, the new water main on Huntley/Main will be connected to the existing water main.  Nicor utility work will continue North of Main Street on IL Route 31, on the west side of the road.  Currently, the contractor is still waiting for their work plan to be approved by Nicor due to the construction work occurring over and around Nicor’s high pressure gas main.