Project Progress

10/18/2019 IL Route 31 Construction Update

October 18, 2019
Placement of the asphalt base and binder was completed on Huntley Road, East of IL Route 31. All driveway aprons on the North side of Huntley Road will be completed by the end of the day. Next week, work is anticipated to begin on the shared use path on the North side of Huntley Road. Main Street entrances at Otto Engineering are anticipated to be completed next week.
Read More

10/11/2019 IL Route 31 Construction Update

October 11, 2019
Placement of the asphalt base and binder will occur on Huntley Road, East of IL Route 31 next week. After completion of the asphalt base and binder on Huntley Road, the sidewalk and driveways will be installed.
Read More

10/4/2019 IL Route 31 Construction Update

October 4, 2019
Sections of the retaining wall located at the NE corner of IL Route 31 and Main Street is continuing to be constructed. Concrete driveways and sidewalk will be poured on both North and South Lincoln Avenue. After completion of the driveways and sidewalk on Lincoln Avenue, asphalt will be placed on Lincoln Avenue. Preparation of the roadway base on Huntley Road, west of IL Route 31, is continuing.
Read More

9/27/2019 IL Route 31/Huntley Road Construction Update

September 27, 2019
Utility relocation work is continuing on IL Route 31. The wall of the retaining wall located at the NE corner of IL Route 31 and Main Street will be poured today. Curb and gutter will be poured on both the North and South sections of Lincoln Avenue on Monday, September 30, 2019.
Read More

North Lincoln Avenue Road Closure and Detour - 9/23/2019 - 9/29/2019

September 20, 2019
Road Closure & Detour – North Lincoln Avenue at Main Street South Lincoln will be re-opened prior to the North Lincoln closure September 23rd (weather dependent). North-Bound Lincoln Ave will be closed from Sept. 23rd to Sept. 29th.
Read More

South Bound Lincoln Avenue Road Closure and Detour at Main Street - 9/16/2019 - 9/22/2019

September 12, 2019
South Bound Lincoln Avenue at Main Street will be closed beginning September 16, 2019 through September 22, 2019.
Read More

09/05/2019 IL Route 31 Construction Update

September 5, 2019
Utility relocation work is continuing on IL Route 31. The retaining wall footing is expected to be poured on Friday. Work will continue on forming the wall portion of the retaining wall after the retaining wall footing pour at the NE corner of IL Route 31 and Main Street.
Read More

08/30/2019 IL Route 31 Construction Update

August 30, 2019
Utility relocation work is continuing on IL Route 31. Excavation for the retaining wall located at the NE corner of IL Route 31 and Main Street has been completed and footing forms are being set.
Read More

August 27, 2019 South Lincoln Avenue Closure and Detour

August 26, 2019
Road Closure & Detour – Main Street and Lincoln Avenue Tuesday, August 27th
Read More

August 26, 2019 South Lincoln Avenue Road Closure and Detour

August 25, 2019
Road Closure & Detour – Main Street and Lincoln Avenue Monday,August 26th • South-Bound Lincoln Ave. will be closed during daytime hours.
Read More

08/22/2019 IL Route 31 Construction Update

August 23, 2019
Utility relocation work is continuing on both Lincoln Avenue and IL Route 31. Storm sewer work continuing on Lincoln Avenue. . Expect a daily road closures and detours of Lincoln Avenue. Work continues on the retaining wall located at the NE corner of IL Route 31 and Main Street.
Read More

August 22 and 23 South Bound Lincoln Avenue Closure and Detour

August 21, 2019
Thursday, August 22nd & Friday, August 23rd, South-Bound Lincoln Ave. will be closed during daytime hours.
Read More

August 19, 2019 South Bound Lincoln Avenue Road Closure and Detour

August 19, 2019
South-Bound Lincoln Ave. will be closed during daytime hours August 19, 2019.
Read More

August 20 and 21, 2019 South Bound Lincoln Avenue Road Closure and Detour

August 19, 2019
 Tuesday,August 20th & Wednesday, August 21st South-Bound Lincoln Ave. will be closed during daytime hours.
Read More

August 15 and 16 South Bound Lincoln Avenue Road Closure and Detour

August 14, 2019
Thursday,August 15th & Friday, August 16th South-Bound Lincoln Ave. will be closed during daytime hours.
Read More

August 14, 2019 North Bound Lincoln Avenue Road Closure and Detour

August 13, 2019
August 14, 2019 North-Bound Lincoln Ave will be closed during daytime hours.
Read More

08/08/2019 IL Route 31 Construction Update

August 8, 2019
Water main services have been completed on South Lincoln Avenue. Water main service installation to begin on North Lincoln tomorrow and continuing next week. Utility relocation is continuing. Expect a daily road closures and detours of North Lincoln Avenue.
Read More

August 9, 12 and 13 North Bound Lincoln Avenue Closure and Detour

August 8, 2019
Friday, August 9th, Monday August 12th & Tuesday,August 13th North-Bound Lincoln Ave will be closed during daytime hours
Read More

August 7 and 8, 2019 South Bound Lincoln Avenue Road Closure

August 6, 2019
 Wednesday, August 7th & Thursday, August 8th, South-Bound Lincoln Avenue will be closed during daytime hours.
Read More

07/31/2019 IL Route 31 Construction Update

July 31, 2019
Water main services on Lincoln Avenue expected to be completed by the end of the week followed by installation of sanitary service installation on Lincoln Avenue. This work will require periodic closures of Lincoln Avenue. Filling of the abandoned 16" water main with a cement/grout material is anticipated to be completed by the end of the week.
Read More

July 30, 2019 South Lincoln Road Closure and Detour

July 30, 2019
July 30, 2019, South-Bound Lincoln Ave will be closed during daytime hours.
Read More

July 31, 2019 North Lincoln Road Closure and Detour

July 30, 2019
North Bound Lincoln Avenue will during daytime hours July 31,2019
Read More

JULY 26 ROAD CLOSURE & POSTED DETOUR INFORMATION

July 26, 2019
South-Bound Lincoln Avenue will be closed during daytime hours.
Read More

07/22/2019 IL Route 31 Construction Update

July 22, 2019
Water main service and sanitary service installation continues. Filling of the abandoned 16" water main is anticipated to be completed by the end of the week. Comcast and AT&T relocation work is continuing. Excavation for the retaining wall at the Northeast corner of IL Route 31 and Main Street will begin within the next week or two after utility relocation.
Read More

07/12/2019 IL Route 31 Construction Update

July 12, 2019
Water main service and sanitary service installation are expected to be installed beginning Monday. Filling of the abandoned 16" water main is anticipated to be completed next week. Comcast and AT&T relocation work is continuing.
Read More

Weekend Utility Relocation Work Notice

July 12, 2019
Please be aware, Blue Jay Communications, a contractor for AT&T, will be working within the IL Route 31 and Huntley Road construction zone both Saturday's and Sunday's the next few weekends in order to relocate AT&T facilities that are in conflict with the existing construction project. Blue Jay Communication will be working weekend's until the AT&T utility relocation work has been completed.
Read More

07/05/2019 IL Route 31 Construction Update

July 5, 2019
Water main installation has been completed on Lincoln. Water and sanitary sewer services are expected to be completed in the next two weeks.‍ Storm sewer and sanitary sewer work to be completed within the next two weeks.
Read More

06/28/2019 IL Route 31 Construction Update

June 28, 2019
Water main installation continuing on Lincoln, South of Main Street. Water and sanitary sewer service expected to be installed in the next two weeks.‍
Read More

Road Closure & Detour - Main Street and Lincoln Road

June 26, 2019
CONSTRUCTION NOTICE – RELEASE DATE: June 26, 2019 IL-31 / Huntley-Road Improvement Project Road Closure & Detour – Main Street and Lincoln Avenue
Read More

06/21/2019 IL Route 31 Construction Update

June 21, 2019
Water main installation continuing on Lincoln, South of Main Street. Traffic signal work at the NW corner of IL Route 31 and Main Street is anticipated next week along with continued utility work at the same intersection corner.
Read More

06/13/2019 IL Route 31 Construction Update

June 13, 2019
16" water main connections on IL Route 31 will be completed by the end of the week and water main installation to continue on Lincoln Avenue North of Main Street. Sanitary sewer lining began today on IL Route 31 and will continue next week.
Read More

06/07/2019 IL Route 31 Construction Update

June 7, 2019
Water main installation to continue on Lincoln Avenue North of Main Street.
Read More

05/30/2019 IL Route 31 Construction Update

May 30, 2019
Storm Sewer installation is continuing on IL Route 31. Installation of water main at the intersection of Main Street and Lincoln has been completed. Pavement removal completed on Lincoln Avenue both North and South of Main Street. Water main installation to begin on Lincoln Avenue North of Main Street.
Read More

05/24/2019 IL Route 31 Construction Update

May 24, 2019
Storm Sewer installation is continuing on IL Route 31. Installation of water main at the intersection of Main Street and Lincoln is also continuing. Work anticipated to begin within next two weeks include sanitary sewer lining and water main installation on Lincoln.
Read More

MAY 20 - 24 ROAD CLOSURE & POSTED DETOUR INFORMATION

May 15, 2019
ROAD CLOSURE & POSTED DETOUR INFORMATION
Read More

05/09/2019 IL Route 31 Construction Update

May 9, 2019
Due to the weather conditions over the past week, the contractor has the same schedule as last week.
Read More

05/02/2019 IL Route 31 Construction Update

May 2, 2019
Due to the weather conditions over the past week, the contractor has the same schedule as last week.
Read More

04/25/2019 IL Route 31 Construction Update

April 25, 2019
Storm Sewer installation is continuing on IL Route 31. Installation of water services beginning on IL Route 31. Work anticipated to begin within next two weeks include sanitary sewer lining and excavation and placement of the roadway base in the areas were roadway pavement had previously been removed.
Read More

04/17/2019 IL Route 31 Construction Update

April 17, 2019
Storm Sewer installation continuing on IL Route 31, pavement patching on Lincoln Avenue, South of Main Street, temporary pavement widening on Main Street, East of Lincoln Avenue and earth excavation and stone placement on Main and IL Route 31 anticipated in the next two weeks.
Read More

04/05/2019 IL Route 31 Construction Update

April 5, 2019
16" water main installation continuing on IL Route 31 North of Main Street, 16" water main installation completed on Main Street between Lincoln and IL Route 31 and storm sewer installation beginning on Main Street between Lincoln and IL Route 31.
Read More

03/27/2019 IL Route 31 Construction Update

March 27, 2019
16" water main installation continuing on IL Route 31 North of Main Street, 16" water main installation continuing on Main Street between Lincoln and IL Route 31, and pavement removal continuing behind the existing concrete barrier walls with installation of storm sewer to follow in the locations of the pavement removal.
Read More

03/20/2019 IL Route 31 Construction Update

March 20, 2019
Sanitary sewer installation is expected to be completed by the end of the week. Pavement breaking has been completed in the areas behind the temporary concrete barriers.
Read More

03/14/2019 IL Route 31 Construction Update

March 14, 2019
Utility relocation work will be completed in the next few weeks. Over the next two weeks you will see an increased construction presence.
Read More

02/19/2019 IL Route 31 Construction Update

February 19, 2019
Utility relocation work is continuing for AT&T, Comcast and ComEd. Over the next week, the project contractor and subcontractors do not expect to be on-site.
Read More

01/23/2019 IL Route 31 Weekly Construction Update

January 23, 2019
Utility relocation work is continuing for AT&T, Comcast and ComEd. Over the next 1 1/2 weeks, the project contractor and subcontractors do not expect to be on-site due to anticipated adverse weather conditions.
Read More

01/16/2019 IL Route 31 Weekly Construction Update

January 16, 2019
Utility relocation work is continuing for AT&T, Comcast and ComEd. Over the next 1 1/2 weeks, the project contractor and subcontactors do not expect to be on-site due to anticipated adverse weather conditions.
Read More

12/20/2018 IL Route 31 Construction Update

December 20, 2018
Pavement saw cutting is currently underway on Northbound IL Route 31 north of Main Street within the lane closure.
Read More

12/13/2018 IL 31 Weekly Construction Update

December 13, 2018
Pavement saw cutting is anticipated to begin on Tuesday on Northbound IL 31 north of Main Street within the lane closure.
Read More

12/05/2018 IL Route 31 Weekly Construction Update

December 5, 2018
New sanitary service installation to residents and businesses on Main Street between Elm and IL Route 31 to begin next week.
Read More

11/29/2018 IL Route 31 Weekly Construction Update

November 29, 2018
New water service installation to residents and businesses on Main/Huntley between Elm and IL Route 31 has been completed.
Read More

11/16/2018 IL Route 31 Weekly Update

November 16, 2018
New water service installation to residents and businesses on Main/Huntley between Elm and IL Route 31 will continue until complete.
Read More

11/08/2018 IL 31 Weekly Construction Update

November 8, 2018
New water service installation to residents and businesses on Main/Huntley between Elm and IL Route 31 will as early as tomorrow.
Read More

11/01/2018 IL Route 31 Construction Update

November 1, 2018
Water main installation on Main/Huntley between Elm and IL Route 31 has been completed. New water services will be installed to residents and businesses as early Monday or Tuesday.
Read More

10/25/2018 IL Route 31 Construction Update

October 25, 2018
Water main installation will continue next week. While removing the second underground storage tank, a third and fourth underground storage tank was identified and removed at NW corner of IL Route 31 and Huntley Road.
Read More

10/18/2018 IL Route 31 Construction Update

October 18, 2018
Removal of the second underground storage tank at NW corner of IL Route 31 and Huntley Road will be completed on Friday.
Read More

10/11/2018 IL Route 31 Construction Update

October 11, 2018
The temporary lane shift that is in place today will be removed by the end of today not withstand any construction related issues with installation of the water main under IL Route 31.
Read More

10/11/2018 Temporary Traffic Switch

October 10, 2018
In an effort to accommodate installation of water main across IL Route 31, Thursday, October 11, 2018, the current north and south bound lanes of IL Route 31 will be shifted to the north bound lane of IL Route 31 from Spruce through the IL Route 31/Main Street intersection to approximately 500’ north of the intersection.
Read More

10/4/2018 Construction Update

October 4, 2018
It should be noted that the Main Street and Lincoln Avenue detours have been implemented.
Read More

10/1/2018 Revised Detour Update

October 1, 2018
My apologies. I spoke to soon regarding the postponement of the detour. The contractor has decided to implement the detours on Main and both northern and southern sections of Lincoln Avenue by the end of the day today.
Read More

10/1/2018 Detour

October 1, 2018
The Main Street and Lincoln Avenue detour that was scheduled to be completed today has been postponed due to rain.
Read More

09/27/2018 Construction and Detour Update

September 27, 2018
Temporary traffic signals were activated at Spruce and IL Route 31, Main/Huntley and IL Route 31 and Elm and Huntley last Thursday and Friday.
Read More

9/20/2018 Construction and Main Street/Lincoln Avenue Detour Update

September 20, 2018
It should be noted that implementation of the Main Street and Lincoln Avenue detour has been delayed to October 1st.
Read More

9/12/2018 Construction Update

September 12, 2018
Water main construction continues on Main Street between Elm and IL Route 31.
Read More

Main Street and Lincoln Avenue Road Closure and Detour

September 12, 2018
September 24th (weather dependent), one-way traffic closures will be in place at the following locations: ‍
Read More

09/06/2018 Construction Update

September 6, 2018
Tree removal has been completed throughout the project. Temporary traffic signal installation at Huntley, Elm and Spruce is continuing.
Read More

08/30/2018 Construction Update

August 30, 2018
Installation of temporary traffic signals have begun at IL Route 31 and Main/Huntley Street.
Read More